Contractor Blamed for Delays in the Paphos-Polis Chrysochous Road Project

February 7, 2025

The Audit Office has blamed the contractor for the delays in the Paphos-Polis Chrysochous road project, stating that the contractor had warned of their intention to terminate the contract. Additionally, concerns have been raised about the Greek judiciary's decision to prohibit payment of guarantees. The delays are significant, with progress on the project below 4% after 20 months. The Audit Office emphasizes the need for immediate resolution of the observed issues.