The new Neonatal Intensive Care Unit at Makarios Hospital is significantly delayed, and its costs have risen from €4 million to at least €6 million. The delay was caused by the contractor's inability to complete the project and the need for additional safety measures from the Fire Department. The Health Organization plans to issue a new tender, aiming to complete the unit by September 2027. However, officials in Parliament expressed concerns that these delays will negatively impact healthcare for newborns and their families.