Kick-off of the Third Phase of the Nicosia Ring Road
October 13, 2025
The third phase of the Nicosia Ring Road is launched, extending 9.4 kilometers from Anthoupoli to the community of Anagyia. The project includes four interchanges and a valley bridge approximately 200 meters long. The tender for the construction was announced on October 10, with a deadline for expressions of interest set for November 21, 2025. Construction is expected to start in June 2026 and will last for 40 months. The estimated cost of the project is €95 million, with €43.4 million funded by the EU.